Central Washington Hospital - Wenatchee, WA

Location: Wenatchee, WA

Central Washington Hospital opened our six-story patient tower on Sunday, May 1, 2011. The tower features 176 patient rooms. The 190,000-square-foot addition includes one story underground and five above, nearly doubling the size of the region's largest trauma facility. The tower houses private patient rooms, a new Mother/Baby Unit and expanded Intensive Care Unit. Apollo Mechanical performed the upgrade to the existing Mechanical Systems for this six-story tower addition to existing hospital structure.

 Slideshow Image
 Slideshow Image
 Slideshow Image
 Slideshow Image
Relevant Project Details:
  • Apollo’s total labor to complete the project is 149,000 man hours. That equates to 71 years worth of labor, all completed without a single time loss injury
  • 185,736 lineal feet of piping ranging in size from 18” diameter to ½”diameter. That is over 35 miles of piping installed, total fitting count is roughly 63,180
  • 322,746 pounds of duct has been installed in the tower, that is 161 tons of duct built, transported and installed in 10 months
  • There is a total of 2087 grilles, resisters and diffusers and over 1287 new plumbing fixtures in the project
  • New CUP containing chiller and generator rooms
  • Upgrade to existing heating system including new firetube boiler, DA and Surge
Apollo was rated number 1 for safest company in Washington, 2010-2011

Apollo Mechanical
1201 W Columbia Drive
Kennewick WA 99336
P: 509.586.1104

© Copyright 2019. All rights reserved.